August 23, 2022 – Harris County Commissioners Court approved a change in contract adding 217 calendar days and $410,168 to the contract amount in support of this project.
August 2, 2022 – Harris County Commissioners Court authorized a change in contract for the excavation of the Genoa Red Bluff Stormwater Detention Basin – Phase 1, adding 32 calendar days with no change to the contract amount.
April 5, 2022 – Harris County Commissioners Court authorized a change in contract for the construction of the Genoa Red Bluff Stormwater Detention Basin – Phase 1, adding 32 calendar days with no change to the contract amount.
June 29, 2021 – Harris County Commissioners Court authorized $2,111,794 for for phase 1 excavation of this project.
June 8, 2021 – Harris County Commissioners Court authorized an agreement in the amount of $379,354 with an engineering firm for services in support of this project.
April 27, 2021 – Harris County Commissioners Court has authorized advertisement for bids for Phase 1 construction of this project.
July 14, 2020 – Harris County Commissioners Court authorized negotiations with an engineering firm for preliminary engineering, design, bidding and construction stage engineering services for development of the B509-04-00 compartment.
May 19, 2020 - Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes project title to include B509-03-00 and to remove the incorrect basin name. B509-03-00 right-of-way is immediately adjacent to B509-04-00.
April 28, 2020 - Harris County Commissioners Court authorized and initiated this project.