January 10, 2023 – Harris County Commissioners Court authorized the Flood Control District to accept a $6,536,842 grant for the Blue Bell Stormwater Detention Basin, P518-21-00, from the Federal Emergency Management Agency, with a required match of $2,786,198.
October 25, 2022 – Harris County Commissioners Court authorized a joint funding agreement with Harris County for Aldine Mail Route Improvements in connection with this project.
October 25, 2022 – Harris County Commissioners Court approved the supplementation utilization of funds from the Harris County Flood Resilience Trust in the amount of $3,853,184, in support of this project.
September 27, 2022 - Harris County Commissioners Court approved a change in the construction contract resulting in an addition of 31 calendar days with no change to the contract amount.
September 13, 2022 – Harris County Commissioners Court approved a change to the construction contract, adding 36 calendar days and $900,250 to the contract amount.
April 26, 2022 – Harris County Commissioners Court approved a change in the construction contract for this project, adding 120 calendar days and $1,400,878 to the contract amount.
March 8, 2022 - Harris County Commissioners Court approved a change in contract to add 34 calendar days and no change to the contract amount for construction stage service in support of this project.
January 25, 2022 – Harris County Commissioners Court awarded a contract in the amount of $4,772,320 with an engineering firm for construction stage services in support of the P118-21-00 Drainage Improvements Phase II project.
January 25, 2022 – Harris County Commissioners Court authorized negotiation of an interlocal agreement between the Flood Control District and the Texas Department of Transportation to modify and maintain the P518-07-00 Stormwater Detention Basin as part of the P118-21-00 Drainage Improvements Phase II project.
January 4, 2022 – Harris County Commissioners Court authorized the acquisition of a 20-foot-wide tract of land in support of this project.
December 14, 2021 – Harris County Purchasing Agent has scheduled construction bidding for Phase 2 of this project.
June 8, 2021 – Harris County Commissioners Court awarded a $5,913,715 contract for construction of the P518-11-00 stormwater detention basin (Phase 1).
March 30, 2021 – Harris County Commissioners Court authorized advertisement for bidding on construction of the P518-11-00 stormwater detention basin.
June 30, 2020 - Harris County Commissioners Court authorized the Flood Control District to revise the scope of services and notice to real property owner document in support of drainage improvements.
May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update corrects project title and funding to reflect project consolidation with Bond ID C-02; project funding also updated based on draft report information.
March 10, 2020 - Harris County Commissioners Court authorized the acquisition of five tracts of land in support of this project.
January 28, 2020 - Harris County Commissioners Court accepted a Preliminary Engineering Report for this project.
February 26, 2019 – Harris County Commissioners Court authorized an agreement between Harris County Community Services, Harris County Commissioner Precinct 2 and the Harris County Flood Control District to use $9.58 million in Community Development Block Grant-Disaster Recovery program funds in support of this project.
November 13, 2018 – Harris County Commissioners Court approved a $604,471 contract with an engineering firm for preliminary engineering of this project
December 3, 2018 – Project Kick-off Meeting