May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update consolidates project with Bond ID C-27 into a single project.
November 13, 2018 – Harris County Commissioners Court approved an $864,985 agreement with an engineering firm to conduct preliminary engineering in support of this project
August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete a preliminary engineering report in support of this project
August 28, 2018 – Harris County Commissioners Court authorized and initiated this project