C-48 Grand Parkway at Clay Stormwater Detention Basin

C-48 Grand Parkway at Clay Stormwater Detention Basin
Menu

Recent Actions

August 2, 2022 – Harris County Commissioners Court authorized an agreement to provide design and bidding stage engineering services in the amount of $975,707 in support of a stormwater detention basin on South Mayde Creek.

October 26, 2021 - Harris County Commissioners Court authorized negotiations with an engineering firm for design, bidding, and construction stage services in support of this project.

October 26, 2021 - Harris County Commissioners Court accepted a preliminary engineering report and authorized the design and construction stages in support of this project.

September 29, 2020 – Harris County Commissioners Court authorized the acquisition of three tracts of land for this project.

March 10, 2020 - Harris County Commissioners Court authorized an $962,101 agreement for preliminary engineering in support of this project.

December 3, 2019 – Harris County Commissioners Court approved negotiations with an engineering firm for preliminary engineering services in support of this project 

December 3, 2019 – Harris County Commissioners Court added HCFCD Unit U501-07-00 to the Flood Control District’s stormwater management system for identification purposes.

September 24, 2019 – Harris County Commissioners Court authorized and initiated this project

Bond List

List of 2018 Bond Projects

Project Lifecycle

Every flood damage reduction project is unique. Yet each project begins and ends, with common and predictable milestones along the way. Whether a project moves forward – and how quickly – depends on many factors, including the availability of funding at each milestone, shifting community priorities for flood damage reduction, and other changing circumstances (such as the price of trees or concrete) from year to year.