November 15, 2022 – Harris County Commissioners Court approved negotiations for materials engineering and testing services in support of this project.
May 25, 2021 - Harris County Commissioners Court authorized a $836,268.50 agreement with a firm for engineering services in support of this project.
April 27, 2021 - Harris County Commissioners Court accepted the Preliminary Engineering Report and authorized the design and construction stages for this project.
May 19, 2020 - Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update corrects project title by removing the word "Planning" from original title.
November 13, 2018 – Harris County Commissioners Court approved an $810,161 agreement with an engineering firm to conduct preliminary engineering support of this project