C506-02-00 Crenshaw Stormwater Detention Basin

C506-02-00 Crenshaw Stormwater Detention Basin
Menu

Recent Actions

  • April 5, 2022 – Harris County Commissioners Court awarded a contract in the amount of $4,822,417 for construction of the Crenshaw Stormwater Detention Basin – Phase II.
  • February 22, 2022 – Harris County Commissioners Court accepted transmittal of this project, which has been scheduled for advertisement of construction bidding.
  • March 30, 2021 – Harris County Commissioners Court authorized the purchase of a tract of land in support of this project.
  • January 26, 2021 – Harris County Commissioners Court authorized a $447,243 agreement for engineering design, bidding and construction stage engineering services for this project.
  • December 1, 2020 - Harris County Commissioners authorized the acquisition of a tract of land in support of this project.
  • August 25, 2020 – Harris County Commissioners Court authorized the Flood Control District to negotiate an agreement for Phase II design, bidding, and construction phase engineering services in support of this project.
  • August 11, 2020 – Harris County Commissioners Court approved an interlocal agreement with the City of Houston for this project.

Virtual Community Engagement Meeting

The Harris County Flood Control District held a Community Engagement Meeting for Crenshaw Stormwater Detention Basin and Arlington Heights projects in Sims Bayou.

Date: Thursday, October 28, 2021
Time: 6:30 – 7:30 p.m.

Meeting Summary Presentation Meeting Video