
 |
 |
 |
Current News |
 |
 |
 |
May 09, 2013
February 27, 2013
February 13, 2013
February 07, 2013
February 05, 2013
February 04, 2013
January 30, 2013
January 09, 2013
January 08, 2013
January 08, 2013
|
 |
 |
|
|
2012 News Archive
|
|
|
|
December 17, 2012
November 26, 2012
October 30, 2012
October 25, 2012
September 20, 2012
September 17, 2012
August 16, 2012
August 1, 2012
July 14, 2012
July 9, 2012
June 25, 2012
May 29, 2012
May 24, 2012
May 15, 2012
May 14, 2012
May 10, 2012
April 19, 2012
April 19, 2012
April 9, 2012
April 9, 2012
March 15, 2012
March 8, 2012
February 29, 2012
February 16, 2012
|
 |
 |
 |
 |
2011 News Archive |
 |
 |
 |
November 28, 2011
November 03, 2011
October 25, 2011
September 28, 2011
September 02, 2011
September 01, 2011
August 30, 2011
August 23, 2011
August 12, 2011
August 08, 2011
July 01, 2011
June 20, 2011
June 17, 2011
May 26, 2011
May 25, 2011
May 23, 2011
May 19, 2011
May 9, 2011
April 18, 2011
April 6, 2011
March 30, 2011
February 14, 2011
February 2, 2011
|
 |
 |
 |
 |
2010 News Archive |
 |
 |
 |
December 15, 2010
December 15, 2010
October 18, 2010
October 11, 2010
October 06, 2010
October 4, 2010
October 4, 2010
October 4, 2010
October 4, 2010
July 27, 2010
July 21, 2010
July 8, 2010
July 1, 2010
July 1, 2010
July 1, 2010
June 30, 2010
June 3, 2010
February 11, 2010
February 8, 2010
February 1, 2010
January 27, 2010
|
 |
 |
 |
 |
2009 News Archive |
 |
 |
 |
November 25, 2009
November 24, 2009
September 30, 2009
September 18, 2009
August 26, 2009
July 21, 2009
July 8, 2009
June 30, 2009
June 22, 2009
June 18, 2009
June 3, 2009
April 24, 2009
April 1, 2009
March 27, 2009
|
 |
 |
 |
 |
2008 News Archive |
 |
 |
 |
December 8, 2008
September 18, 2008
July 2, 2008
May 29, 2008
April 16, 2008
March 31, 2008
March 25, 2008
March 21, 2008
March 3, 2008
February 13, 2008
February 8, 2008
|
|
 |
 |
 |
2007 News Archive |
 |
 |
 |
 |
2006 News Archive |
 |
 |
 |
 |
2005 News Archive |
 |
 |
 |
 |
2004 News Archive |
 |
 |
 |
 |
2003 News Archive |
 |
 |
 |
 |
 |
|
 |
 |
 |
HARRIS COUNTY FLOOD CONTROL DISTRICT TO COMPLETE 150-ACRE STORMWATER DETENTION BASIN PROJECT ON HORSEPEN CREEK
February 16, 2012
This month the Harris County Flood Control District will launch the final phase of a 150-acre stormwater detention basin project in northwest Harris County that will result in an approximately $9.3 million cost savings to taxpayers.
The stormwater detention basin is located at the upstream end of Horsepen Creek approximately 0.5 miles east of Barker-Cypress Road. The basin is almost completely surrounded by residential neighborhoods, including Canyon Lakes at Stonegate on the basin’s north and west sides and Copper Lakes on the south side.
Heather Saucier, Flood Control District spokeswoman, said the majority of the stormwater detention basin was excavated through an excavation and removal (E&R) agreement with Sprint, Sand & Clay, LLC.
“The company excavated and removed the soil from the site at very little cost to the District,” Saucier said. “We are now moving forward with the final phase of the project, which will complete the excavation and ensure that the stormwater detention basin is fully operational.”
The final phase of the capital project also includes constructing a weir structure and significant re-grading of the detention basin’s slopes.
N&Z Contracting, Inc. was awarded the approximately $1.3 million contract in November 2011. The project will take approximately 100 working days to complete.
When stormwater detention basins are used for flood damage reduction purposes, they are sometimes designed with a weir structure. The weir serves as a spillway whereby stormwater rising in a channel – in this case Horsepen Creek - can spill into the detention basin during times of heavy rain where it will be temporarily stored and slowly released back to the creek.
After the construction of the weir structure and regrading of the detention basin’s slopes, the basin will retain approximately 360 million gallons of stormwater that otherwise might flood homes and businesses and will help reduce flooding risks for those who live downstream along the creek’s banks.
This capital project is in addition to a Flood Control District maintenance project underway downstream on Horsepen Creek. That maintenance project is restoring a 3.25-mile section of Horsepen Creek from State Highway 6 to the Addicks Reservoir in west Harris County.
Work on the maintenance project started in late August 2011 and will be completed in 2012 depending on weather conditions. The Flood Control District’s project includes erosion repair work on Horsepen Creek’s upstream segment and the removal of sediment on the downstream segment that has naturally accumulated in the creek over the years.
ABOUT THE HARRIS COUNTY FLOOD CONTROL DISTRICT
The Harris County Flood Control District provides projects that reduce flooding risks and damages from bayous and creeks, with appropriate regard for community and natural values. With more than 1,500 bayous and creeks totaling approximately 2,500 miles in length, the Flood Control District accomplishes its mission by devising flood damage reduction plans, implementing the plans and maintaining the infrastructure. To learn more about the Flood Control District, visit www.hcfcd.org.
|
 |
|