Inverness Forest Levee

Inverness Forest Levee
Menu

Recent Action

September 27, 2022 – Harris County Commissioners Court initiated a new project for Inverness Forest Levee modifications, using funding from 2018 Bond ID Z-04.

May 11, 2021 – Harris County Commissioners Court approved a $274,000 agreement for engineering services in support of the recertification project.

March 30, 2021 – Harris County Commissioners Court authorized an agreement with Inverness Forest Improvements District, at a cost of $164,000 to the Flood Control District.

February 9, 2021 – Harris County Commissioners authorized the negotiation of an interlocal partnership agreement with Inverness Forest Improvement District in support of this project.

February 25, 2020 - Harris County Commissioners Court authorized negotiations with an engineering firm in support of this project.