September 28, 2021 – Harris County Commissioners Court authorized the acquisition of two tracts of land for the public project known as Stormwater Detention Basin on South Mayde Creek.

March 26, 2019 - Harris County Commissioners Court approved a $500,000 contract with an engineering firm to conduct preliminary engineering in support of this project.

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for preliminary engineering services in support of this project.

September 25, 2018 – Harris County Commissioners Court authorized and initiated this project.

Virtual Community Engagement Meeting

A Community Engagement meeting for this project was held on November 14, 2019.

Summary Presentation Virtual Meeting Video

Project Lifecycle

Every flood damage reduction project is unique. Yet each project begins and ends, with common and predictable milestones along the way. Whether a project moves forward – and how quickly – depends on many factors, including the availability of funding at each milestone, shifting community priorities for flood damage reduction, and other changing circumstances (such as the price of trees or concrete) from year to year.