June 29, 2021 - Harris County Commissioners Court authorized a change in contract with no change to contract amount for this project.
January 26, 2021 - Harris County Commissioners Court approved a contract change adding 31 calendar days and $423,552 to the construction contract amount for this project.
October 27, 2020 - Harris County Commissioners Court authorized the Flood Control District to negotiate an agreement for design, bidding, and construction phase engineering services to replace a destroyed concrete spillway and related channel repairs in support of this project.
September 29, 2020 – Harris County Commissioners Court authorized a change in contract to add 74 calendar days and no additional funds for construction services in support of this project.
August 25, 2020 – Harris County Commissioners Court authorized a change in contract to add 19 calendar days and no additional funds for construction services in support of this project.
August 11, 2020 – Harris County Commissioners Court approved an additional $90,840 for construction activities.
May 19, 2020 - Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes funding details to reflect engineers estimate and pending construction bid.
April 28, 2020 - Harris County Commissioners Court authorized an additional $60,737 for construction of this project.