March 8, 2022 - Harris County Commissioners Court acknowledged substantial completion of the construction stage of this project.
December 14, 2021 – Harris County Commissioners Court approved a change in the construction contract for this project, with no change in the contract amount.
August 24, 2021 – Harris County Commissioners Court approved a Change in Contract No. 1 with an engineering firm adding 89 calendar days and an increase of $873,324 to the contract amount in support of this project.
October 13, 2020 – Harris County Commissioners Court authorized $3,495,867 for wetland construction subject to applicable bonds.
June 6, 2020 – Harris County Commissioners Court approved a $103,190 agreement for construction phase engineering services in support of this project.
May 19, 2020 - Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update corrects project title to reference mitigation bank K700-01-00 instead of K700-02-00.
January 28, 2020 - Harris County Commissioners Court authorized negotiations with an engineering firm for bidding and construction phase engineering services in support of this project
August 27, 2019 – Harris County Commissioners Court authorized a mitigation banking instrument, prices for sale of mitigation credits, a conservation easement with Katy Prairie Conservancy, and construction in support of this project
June 3, 2019 – The Final Mitigation Banking Instrument was submitted to the U.S. Army Corps of Engineers for review by local and federal agencies.
December 11, 2018 – The first draft Mitigation Banking Instrument was submitted to the U.S. Army Corps of Engineers for review by local and federal agencies.
July 25, 2017 – The Prospectus was submitted to U.S. Army Corps of Engineers and put on Public Notice.
June 23, 2015 - Harris County Commissioners Court approved a $199,388.00 agreement with an environmental firm for specialized evaluation and planning services in support of this project.