June 30, 2020 - Harris County Commissioners Court acknowledged substantial completion of Bond ID F-40, the Lower Greens Bayou regional detention embankment and control structure project.
March 24, 2020 – Harris County Commissioners Court approved an additional $35,193 for construction of this project.
February 25, 2020 – Harris County Commissioners Court approved an additional $27,624 for construction of this project.
November 12, 2019 – Harris County Commissioners Court approved an additional
$30,237 for construction of this project.
September 24, 2019 – Harris County Commissioners Court authorized a $142,845 contract amendment with an engineer firm in support of this project.
January 29, 2019 – Harris County Commissioners Court approved a $92,921 agreement with an engineering firm for materials engineering and testing services in support of this project.
December 4, 2018 – Harris County Commissioners Court approved a $2.4 million contract for construction of this project.
August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct materials engineering and testing services in support of this project.