December 13, 2022 - Harris County Commissioners Court approved a change in the construction contract adding 36 calendar days and an additional $39,804 to the contract amount.
August 2, 2022 – Harris County Commissioners Court authorized a change in contract, adding 30 calendar days and resulting in the addition of $11,759 to the contract amount, in support of this project.
May 24, 2022 – Harris County Commissioners Court approved a change in contract adding 86 calendar days and $18,456 to the construction contract amount.
July 14, 2020 – Harris County Commissioners Court authorized the purchase of $29,400 in wetlands mitigation credits from the Greens Bayou Wetlands Mitigation Bank in support of this project.
June 9, 2020 – Harris County Commissioners Court approved a $166,000 agreement with an engineering firm for materials engineering and testing services in support of this project.
June 6, 2020 – Harris County Commissioners Court approved a $166,000 agreement for materials engineering and testing services in support of this project.
May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Updates corrects project title to include "stormwater detention" and “improvements”; funding updated to reflect engineers estimate and pending construction bid; and partner funding amount was removed as none was secured.
April 28, 2020 – Harris County Commissioners Court awarded a $14.2 million contract for construction of this project.
March 24, 2020 – Harris County Commissioners Court authorized negotiations for materials engineering and testing services in support of this project.
March 10, 2020 – Harris County Commissioners Court authorized an additional $129,592 for engineering services in support of this project.
December 17, 2019 – Harris County Commissioners Court authorized the purchase of wetland mitigation credits from the Greens Bayou Wetlands Mitigation Bank in support of this project.
November 12, 2019 – Harris County Commissioners Court accepted a preliminary engineering report and authorized the design and construction of this project.
November 13, 2018 – Harris County Commissioners Court approved a $739,525 agreement with an engineering firm for final design of this project.
August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project.