C-58 Drainage Improvements Along F101-06-00

C-58 Drainage Improvements Along F101-06-00
Menu

Recent Action

January 4, 2022 – Harris County Commissioners Court accepted a Preliminary Engineering Report in support of this project.

March 10, 2020 – Harris County Commissioners Court authorized a $514,791 agreement for preliminary engineering in support of this project.

January 29, 2019 – Harris County Commissioners Court authorized initiation of this project.

Project Description

This project includes right-of-way acquisition, design and construction of general drainage improvements along HCFCD Unit F101-06-00, a tributary in the San Jacinto River & Galveston Bay watershed. In January 2022, following a December 2020 Bond Program Community Engagement Meeting that took comments from the public, a Preliminary Engineering Report (PER) for this project was transmitted to Harris County Commissioners Court. This project is now in the Design stage.