June 28, 2022 – Harris County Commissioners Court authorized the acquisition of a tract of land for the purpose of floodplain preservation.
May 10, 2022 – Harris County Commissioners Court approved purchase of a tract of land in support of this project.
April 5, 2022 – Harris County Commissioners Court authorized the acquisition of a tract of land for the purpose of floodplain preservation.
February 22, 2022 –Harris County Commissioners Court approved the acquisition of a tract of land for the purpose of floodplain preservation.
January 4, 2022 –Harris County Commissioners Court authorized the acquisition of one tract of land in support of this project.
November 9, 2021 – Harris County Commissioners Court has approved the acquisition of one tract of land for floodplain preservation.
August 10, 2021 – Harris County Commissioners Court authorized the acquisition of one tract of land in support of this project
May 11, 2021 - Harris County Commissioners Court authorized the acquisition of two tracts of land for the purpose of floodplain preservation.
December 1, 2020 - Harris County Commissioners authorized the acquisition of four tracts of land in support of this project.
September 15, 2020 – Harris County Commissioners Court authorized the acquisition of one tract of land for this project.
August 25, 2020 – Harris County Commissioners Court authorized the purchase of tract J100-00-00-36-008.0 in support of this project.
July 28, 2020 – Harris County Commissioners Court authorized the acquisition of one tract of land for this project.
October 23, 2018 – Harris County Commissioners Court authorized and initiated this project