C-14 Fairbanks-North Houston Stormwater Detention Basin (North)

C-14 Fairbanks-North Houston Stormwater Detention Basin (North)
Menu

Recent Actions

October 27, 2020 - Harris County Commissioners Court authorized the purchase of eight tracts of land in support of this project.

August 11, 2020 – Harris County Commissioners Court approved an additional $90,760 for construction of this project.

June 30, 2020 - Harris County Commissioners Court acknowledged substantial completion of Bond ID C-14, White Oak Bayou federal flood control project, Discrete Segment 01A for the Fairbanks North Houston detention basin.

June 25, 2019 – Harris County Commissioners Court approved an additional $5,850 for this project. 

June 25, 2019 – Harris County Commissioners Court approved an additional $5,850 for materials testing. 

February 26, 2019 – Harris County Commissioners Court authorized the purchase of wetlands mitigation credits from the Greens Bayou Wetlands Mitigation Bank in support of this project. 

February 12, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of this project. 

January 29, 2019 – Harris County Commissioners Court authorized Award to Sprint Sand and Clay.

Bond Program List

List of 2018 Bond Projects

PROJECT LIFECYCLE

Every flood damage reduction project is unique. Yet each project begins and ends, with common and predictable milestones along the way. Whether a project moves forward – and how quickly – depends on many factors, including the availability of funding at each milestone, shifting community priorities for flood damage reduction, and other changing circumstances (such as the price of trees or concrete) from year to year.