June 29, 2021 – Harris County Commissioners Court authorized $250,000 for a feasibility study for this project.
April 27, 2021 – Harris County Commissioners Court authorized the Flood Control District to negotiate for engineering services for a feasibility study to evaluate the benefits of channel modifications from Fondren Rd. to Gessner Rd.
December 15, 2020 – Harris County Commissioners Court authorized the initiation of this project.
May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update adds the words "on Brays Bayou" to project title.