Exciting news for our community! The Harris County Flood Control District is breaking ground on a regional stormwater detention basin that will help reduce flood risks and improve stormwater management in the White Oak Bayou watershed.
Construction on the Yale Stormwater Detention Basin is set to begin in February 2025 near the intersection of Yale Street and West Tidwell Road. This project is a step in enhancing flood risk reduction for the area, as it will provide stormwater storage and support future channel conveyance improvements along Little White Oak Bayou.
The project will include excavation and soil removal, as well as the creation of a unique island feature that will not only enhance water quality but also provide a habitat for birds and other wildlife. Once completed, the detention basin will have the capacity to store approximately 71.4 acre-feet of stormwater, helping to reduce the risk of flooding during heavy rain events.
The Flood Control District remains committed to making our communities safer and keeping residents informed about ongoing efforts to reduce flood risks. For more details about this project and others, visit www.hcfcd.org/yale.
Thank you for your support as we build toward a more resilient future for Harris County!
Project at a Glance:
Project ID: E501-03-00-E001
Precinct: 2
Contractor: A Morfin Trucking, LLC
HCFCD Contract Amount: $3.2 million
Contract Start: February 2025
Contract Duration: 381 days