image

Construction Advisory: Drainage Repairs in Greens Bayou Watershed

In an effort to keep you informed about the Harris County Flood Control District’s continuing maintenance in the Greens Bayou watershed, we want to update you on an upcoming project.

In fall 2022, the Harris County Flood Control District (HCFCD) will begin a channel maintenance project along HCFCD Unit# P130-00-00 between Wilson Road and Mesa Drive. The project will address the channel conveyance capacity issues by restoring the channel back to its original design capacity.

Construction equipment will access the work area via Mesa Drive.  Motorists are urged to be alert to truck traffic when passing near construction access points and along truck routes. The Flood Control District appreciates your patience through the duration of this project. More information about the Flood Control District’s maintenance projects can be found at hcfcd.org/maintenance. Should you have any questions or comments, please visit hcfcd.org/contact-us.
 

Garners Bayou System Repairs and Channel Rehabilitation
Project ID: P130-00-00-X026
Precinct: 1
Contractor: Texas Dewatering, LLC
Contract Amount: Approximately $5.2 million 
Construction Start: Fall 2022
Construction Duration: 360 days