Project Name: E125-00-00-X007 Channel Repairs
Precinct: 4
Contract Amount: Approx. $2.7 million
Construction Start: Winter 2021
Construction Duration: 411 days


Project Description
In Winter 2021, the Flood Control District will begin construction in your area on a maintenance project that will repair the channel from Woodwind Lakes Drive to Lake Lane. Construction equipment will access the work area via Lake Lane and Woodwind Lakes Drive. Motorists are urged to be alert to truck traffic when passing near construction access points and along truck routes. The Flood Control District appreciates your patience through the duration of this project. More information may be available on the Flood Control District’s website, www.hcfcd.org/maintenance. Should you have any questions or comments, please visit www.hcfcd.org/contact-us.