In an effort to keep you informed about the Harris County Flood Control District’s continuing maintenance in the Buffalo Bayou watershed, we want to update you of a construction project.
Project Name: W167-04-00-X005 Channel Conveyance Improvements Phase 1
Package ID: Z100-00-00-X281
Project ID: W167-04-00-X005
Precinct: 3
Contractor: LECON
Contract Amount: Approx. $1,762,000
Construction Start: Summer 2021
Construction Duration: 180 days
Project Description
In Summer 2021, the Flood Control District will begin construction in your area on a maintenance project that will address erosion and slope failure along the approximate 10,000-ft reach of HCFCD Unit# W167-04-00.
Construction equipment will access the work area via Dairy Ashford Road. Motorists are urged to be alert to truck traffic when passing near construction access points and along truck routes. The Flood Control District appreciates your patience through the duration of this project.
More information may be available on the Flood Control District’s website, www.hcfcd.org/maintenance. Should you have any questions or comments, please visit www.hcfcd.org/contact-us.