Mud Gully (Beamer Ditch) Channel Conveyance Improvements Update

The Harris County Flood Control District would like to provide the following construction update on Mud Gully (Beamer Ditch) Project ID A120-00-00-C003:

The Harris County Flood Control District would like to provide the following construction update on Mud Gully (Beamer Ditch) Project ID A120-00-00-C003:

• Progress on Mud Gully channel conveyance improvements currently remains on hold.

• The Harris County Flood Control District is working through a required legal process that began when the construction contractor’s lack of progress forced the Flood Control District to declare the Mud Gully project abandoned and the contractor surrendered the right to remain in possession and control of the work.

• Currently, the contractor’s surety and the Flood Control District are finalizing an agreement that will allow a new contractor to finish the project. 

• Once finalized, the agreement will be submitted to Harris County Commissioners Court for approval.

• The Flood Control District is aiming to resume construction by early 2023

• In the interim, the Flood Control District has been notified of maintenance concerns and will continue to implement mowing and debris removal as needed.

• The Harris County Flood Control District will provide an update on our progress when the agreement is posted for Commissioners Court approval and looks forward to restarting construction as quickly as possible.

Please visit www.hcfcd.org/Mud-Gully for project updates; or to leave a question or comment, click the “Submit A Comment” button located under the Project Description section